New Custom Home in Falmouth

The Valle Group is underway on another new custom home in Falmouth. This 2,480SF home has a project duration of about 8 months. Keep an eye on this page for progress updates.

Project Manager: Wes Lohr

Site Supervisor: Scott Jacobson

Construction Progress

Framing nearly complete.

Roofing underway.

Exterior sheathing nearly complete.

Windows and roof in place, siding underway.

Interior framing and insulation.

Framing of great room.

Second floor framing underway.

Front porch nearly complete.

Exterior nearly complete.

Interior drywall and finish underway.

Windows in place, trim underway.

Interior doors in place.

Garage nearing completion.

Garage exterior siding detail.